August 2020
Site excavation works
September 2020
Creation of new stormwater drain
November 2020
Undergrounding of power lines and removal of power poles
December 2020
Creation of new car parks and road resurfacing
February 2021
Water main relocation
March 2021
Shared path surfacing
April 2021
Final line marking and landscaping